PMP Concepts

11/01/2011 - 7:28am

This is our 42nd post in our new learning series: PMP Concepts

Each post within this series will present a comparison of common concepts that appear on the PMP and CAPM exams.

Budget at Completion versus Variance at Completion

The budget at completion (BAC) is determined at the start of the project. As the project progresses the BAC may need to be revisited based on the project forecast (the estimate at completion – EAC).

As PM you will be responsible for communicating regarding the BAC, the EAC, and the resulting variance at completion (VAC).

0 Comments Continue Reading
10/17/2011 - 7:25am

This is our 41st post in our new learning series: PMP Concepts

Each post within this series will present a comparison of common concepts that appear on the PMP and CAPM exams.

Estimate at Completion versus Estimate to Complete

Although a project budget may be defined, actual project progress may cause a deviation from the pre-determined budget at completion (BAC). Throughout the project, it will be important to provide forecasts as to the amount of money that will actually be spent.

0 Comments Continue Reading
10/02/2011 - 7:22am

This is our 40th post in our new learning series: PMP Concepts

Each post within this series will present a comparison of common concepts that appear on the PMP and CAPM exams.

Schedule Variance versus Schedule Performance Index

Schedule variance (SV) and schedule performance index (SPI) are two earned value calculations that provide a measurement of project progress against the project schedule baseline.

0 Comments Continue Reading
09/20/2011 - 7:19am

This is our 39th post in our new learning series: PMP Concepts

Each post within this series will present a comparison of common concepts that appear on the PMP and CAPM exams.

Cost Variance versus Cost Performance Index

Cost variance (CV) and cost performance index (CPI) are two earned value calculations that provide a measurement of project progress against the project cost performance baseline.

0 Comments Continue Reading
09/10/2011 - 7:16am

This is our 38th post in our new learning series: PMP Concepts

Each post within this series will present a comparison of common concepts that appear on the PMP and CAPM exams.

Corrective versus Preventive Actions versus Defect Repairs

Other than scope changes, change requests may include corrective actions, preventive actions, and defect repairs.

While changes to the project scope, if significant, may update the project baselines (scope, schedule, and cost performance), corrective actions, preventive actions, and defect repairs should not be used to justify a baseline change.

0 Comments Continue Reading
09/01/2011 - 4:13pm

This is our 37th post in our new learning series: PMP Concepts

Each post within this series will present a comparison of common concepts that appear on the PMP and CAPM exams.

Quality Control versus Verify Scope

While most people understand the concept of quality control, differentiating QC from the verify scope process may be a bit more difficult. Both processes are monitoring and controlling processes and both involve the evaluation of the project deliverables.

0 Comments Continue Reading
08/25/2011 - 4:10pm

This is our 36th post in our new learning series: PMP Concepts

Each post within this series will present a comparison of common concepts that appear on the PMP and CAPM exams.

Develop versus Manage the Project Team

There are four processes in the human resources knowledge area: develop human resource plan, acquire project team, develop project team, and manage project team. While developing the human resource plan and acquiring the project team are straightforward, it may not be as intuitive to know the differences between developing and managing the project team.

0 Comments Continue Reading
08/16/2011 - 4:06pm

This is our 35th post in our new learning series: PMP Concepts

Each post within this series will present a comparison of common concepts that appear on the PMP and CAPM exams.

Cost Plus Contracts

Cost-reimbursable (or cost-plus) contracts involve payment to the seller for seller’s actual costs, plus a fee typically representing seller profit. Cost-reimbursable contracts place more risk on the buyer.

Three common types: cost plus fixed fee (CPFF), cost plus incentive fee (CPIF), and cost plus award fee (CPAF)

0 Comments Continue Reading
08/13/2011 - 3:54pm

This is our 34th post in our new learning series: PMP Concepts

Each post within this series will present a comparison of common concepts that appear on the PMP and CAPM exams.

Fixed Price Contracts

Fixed price contracts involve a fixed total price for the product and may also include incentives for meeting or exceeding selected project objectives. The simplest form of a fixed price contract is a purchase order.

0 Comments Continue Reading
08/10/2011 - 3:51pm

This is our 33rd post in our new learning series: PMP Concepts

Each post within this series will present a comparison of common concepts that appear on the PMP and CAPM exams.

Fallback Plan versus Contingent Response Strategy

In project risk management, both fallback plans and contingent response strategies may be developed associated with certain identified risks. Both are planned and developed in advance of the risk event occurring.

0 Comments Continue Reading

Poll

Which PMI Credential/ Certification that you do NOT have are you most interested in pursuing?:

PMI REP
BBB Accredited BusinessFree WebinarsFree Resources

PMP Concepts

PMP Exam Prep Boot CampPMI-RMP Exam Prep Boot CampPMI-ACP Exam Prep Boot CampPrevious ClassesPMP PMI-RMP PMI-ACP Exam Prep Boot Camps

PMP FlashcardsCAPM FlashcardsRMP Flashcardsclick map

Open Enrollment Boot CampsOn-Site Boot CampsPMP Exam Prep ProductsPMP PDUs